Where we work and we worked

ECUADOR

Delsitanisagua Hydroelectric Power Plant

Owner/Client:

Emp. Pública Estrategica Corporación Eléctrica Ecuador "CELEC EP"

Cost of works:

USD $ 258 million

Period of Activity:

2013 - 2017

Delsitanisagua Hydroelectric Project involves the construction and operation of a hydroelectric plant with a capacity of 180MW to be located on the Zamora River, in the Province of Zamora Chinchipe.

— Project Description:

The project will have a regulated volume of 420,000m 3 a 34m-high conventional concrete dam, a power intake channel for a discharge of 42m 3 /s of water, a 8km-long headrace tunnel with an excavation diameter of 4.9m a 70m-high surge shaft with a diameter of 15m, an underground vertical steel penstock with a diameter of 3.3m, an open air power house equipped with three 60MW- each Francis turbines (for a total installed capacity of 180MW), and a 138kV-transmission line for a total length of 30km. The foreseen annual production of electricity is 1200GWh.

— Description of Services:

asic and Detailed Design Review and approval, Construction Supervision.

GEODATA fornisce soluzioni sostenibili e ad alto valore aggiunto per progetti in sotterraneo che soddisfano le crescenti esigenze di trasporto e di sviluppo sostenibile.

Certificazioni

GEODATA è certificata

  • ISO 9001:2015
  • ISO 14001:2015
  • ISO 45001:2018

GEODATA S.p.A.

  • Corso Bolzano 14
    10121 Turin - Italy
  • +39 011.58.10.611
  • +39 011.59.74.40
  • Questo indirizzo email è protetto dagli spambots. È necessario abilitare JavaScript per vederlo.

© 2022 GEODATA SpA - P.IVA 10132770016 | GEODATA Engineering SpA - P.IVA 04639280017 - All rights reserved
Privacy Policy | Cookie Policy | Company details | GEODATA Webmail | Credits