Ferrovie delle Stato – TAV/San Ruffillo JV: Acciona (Necso) - Salini-Ghella
€ 98 million
2004 - 2006
The "Bologna Underpass" is the underground connection in the city of Bologna belonging to the high-speed railway line linking Milan to Naples. The alignment is mainly developed under the embankment of the existing railway line Bologna-Firenze (the main rail link line north-south of Italy) and consists of two single-tube, parallel tunnels crossing the city from the south, near San Ruffillo, to the new railway station in Bologna.
The project involved the mechanical excavation with EPB-TBM of two, 6,112m-long, parallel tunnels with a diameter of 9.4m and with an inter-axis of 15m. The predominantly granular ground conditions, the urban setting and the presence of a strategic surface railway line pose a significant challenge for the construction of this portion of the high speed railway line. In the first part, the tunnels were excavated in argillaceous and sandy deposits under the water table, while the second part in deposits of Savena River, mainly composed by gravel and sands with a certain percentage of fine parts.
Geotechnical Assistance; Detailed Design and Supervision during construction of the tunnels excavated by TBM.
© 2022 GEODATA SpA - P.IVA 10132770016 | GEODATA Engineering SpA - P.IVA 04639280017 - All rights reserved
Privacy Policy | Cookie Policy | Company details | GEODATA Webmail | Credits
Progettazione e realizzazione sito web
vg59* Progetti Multimediali
Corso Bolzano 14 - 10121 Torino
P.I. 10132770016
REA TO-1108130
Capitale sociale i.v. 6.612.840€
PEC: Questo indirizzo email è protetto dagli spambots. È necessario abilitare JavaScript per vederlo.
Corso Bolzano 14 - 10121 Torino
P.I. 04639280017
REA TO-648000
Capitale sociale i.v. 3.469.700€
PEC: Questo indirizzo email è protetto dagli spambots. È necessario abilitare JavaScript per vederlo.
Per la fatturazione elettronica: Questo indirizzo email è protetto dagli spambots. È necessario abilitare JavaScript per vederlo.